Dublin City Council: Sandymount public realm and traffic-calming scheme to move to tender after Part 8 approval
The council is progressing a public realm and traffic-calming scheme through Part 8, with approval sought at the October meeting. If approved, detailed design and tender are expected by the end of this year, with construction targeted for summer 2027.
Dublin City Council · Ireland · 14 September 2026
Verified against the transcript — proposed, not yet agreed
The transcript says they are still “progressing well through the Part 8 process” and hope to “get approval for the part 8 in that October meeting” before “progress[ing] quickly with the detailed design and tender,” so the tender is only planned, not live.
2 of 2 quotes matched verbatim to the official recording · checked 15 September 2026 · This is a verified signal produced by QuorumInsight from a public council meeting. It is not an official procurement or tender notice, is not published or endorsed by the council, and no notice has necessarily been issued on Find a Tender or Contracts Finder. Value, route to market and timing are estimates inferred from what was said and may change. Always verify directly with the authority before acting.
We hope to get approval for the Part 8 in that October meeting and then progress quickly with the detailed design and tender towards the end of this year.
Also said in the meeting
“Tender is as early as possible in 2027 and try and complete construction.”
“We are currently now at your monthly meeting just to give you the update as to where we are on the project.”
What we know
- The scheme is a public realm and traffic-calming project for the northeast side of Sandymount Green.
- The project is currently progressing through the Part 8 process.
- If approved in October, the council expects detailed design and tender towards the end of 2026, with construction targeted for 2027.
How this opportunity developed
Discussed in 2 public meetings before this decision.
- 11 May 2026
Sandymount Green Part 8 timeline
““we intend next week to formally commence the Part 8 process and it will go through the statutory 20 week timeline… targeting the September council meeting to note… and then to the City Council on the 2nd of November.””
- 14 September 2026 · ConfirmedHousing & Traffic Plans
This notice — the confirming discussion.
Why this is a signal, not noise
This is a live pre-tender signal because the meeting confirms the scheme is advancing through Part 8 and names a near-term path into detailed design and tender.
Tags
Source
Housing & Traffic Plans, 14 September 2026
Requires an account with access to this council.
How a supplier could follow up
- Track the October meeting outcome and any Part 8 decision papers for design/tender progression.
- Prepare capability statements for public realm, traffic calming, landscaping, lighting, accessibility and civil/road works.
- Monitor for the tender notice in late 2026 or early 2027 and identify local delivery partners if needed.